Bar chart of starting current for a 30 kW motor with DOL, soft starter, star-delta and VFD

Motor Starting: DOL, Star-Delta, Soft Starter or VFD

A motor started direct-on-line draws six to eight times its rated current for a few seconds. On a stiff transformer supply this rarely matters. On a weak supply, a generator or a long cable it dims the lights, trips other drives and can stall the motor. The starter you pick decides the starting current, the starting torque, the cost and the panel space.

Quick answer: Use DOL for small motors (up to about 5.5–7.5 kW on public LV networks) and wherever the supply is stiff. Use star-delta for larger motors that start with a light load, if the motor has six terminals and a delta winding for the supply voltage. Use a soft starter for pumps and fans that run at fixed speed. Use a VFD when you also need speed control, or the lowest starting current, for example on a generator.

The four methods side by side

MethodStarting current (× In)Starting torqueTypical useWatch out for
DOL6–8 (high-efficiency motors up to 7–9)2–2.5 × ratedSmall motors, stiff supply, fire pumps where the rules call for itVoltage dip, mechanical shock, water hammer
Star-delta2–2.7 (one third of DOL)One third of DOLFans and pumps that start lightly loadedCurrent and torque peak at the open changeover; six motor cables
Soft starter3–4 (set by the current limit)Falls with the square of current (≈ 0.25 of DOL at 3.5 × In)Fixed-speed pumps, fans, compressors, conveyorsHeat in the panel, bypass contactor, weak torque at high current limits
VFD1–1.51–1.5 × rated from standstillVariable flow, generators, high-inertia loads, precise controlHarmonics, EMC cabling, motor cable length, cost

Worked example: 30 kW pump

Motor: 30 kW, 4-pole, 400 V, rated current In ≈ 55 A.
DOL: 7 × 55 = 385 A.
Star-delta: 385 / 3 ≈ 128 A (torque also one third: about 0.7–0.8 × rated).
Soft starter at 3.5 × In: 3.5 × 55 ≈ 193 A (torque ≈ (3.5/7)² = 0.25 of DOL).
VFD at 1.2 × In: ≈ 66 A.
Reading it: a centrifugal pump needs little torque at low speed, so all four can start it. On a 100 kVA generator, DOL would cause a deep dip; a soft starter or VFD is the practical choice.
30 kW motor (In = 55 A) — starting current by method 0 A100 A200 A300 A400 A 385 A 193 A 128 A 66 A In = 55 A DOL7 × In Soft starter3.5 × In Star-delta⅓ of DOL VFD1.2 × In
Starting current for the same 30 kW motor. Note that a soft starter set to 3.5 × In draws more than star-delta, so on a generator star-delta can be the gentler choice.

How to choose in practice

  1. Check the supply. Ask the utility for the largest motor it allows DOL (often 5.5–7.5 kW on public LV networks). On a private transformer, estimate the dip, and on a generator always check it. Why: the supply, not the motor, usually sets the limit.
  2. Check the load torque. Fans and centrifugal pumps need little torque at low speed. Loaded conveyors, crushers and positive-displacement compressors need a lot. Why: star-delta and soft starters reduce torque more than they reduce current.
  3. Ask whether the speed must vary. If flow or pressure should follow demand, a VFD pays for itself in energy on most HVAC pumps and fans. Why: pump and fan power falls roughly with the cube of speed.
  4. Check the motor terminals. Star-delta on a 400 V network needs a 400/690 V motor (delta at 400 V) with six terminals and six cable cores. Why: a 230/400 V motor connected in delta on 400 V burns out.
  5. Check mechanical effects. A DOL start of a large pump causes water hammer, and a DOL stop is even worse. Soft starters and VFDs with controlled stopping solve both. Why: pipework damage costs more than the starter.
  6. Count the panel space and heat. A VFD dissipates about 2–3 % of its power as heat; a soft starter with a bypass contactor dissipates very little while running. Why: a sealed panel may need cooling.
Small variable frequency drive with keypad display showing 60.0 and its front terminal cover open
A small VFD with the terminal cover removed. Supply goes in, a variable-frequency output goes to the motor. The display shows the output frequency in hertz. Photo: C J Cowie, CC BY-SA 3.0, via Wikimedia Commons

Design details that are easy to miss

  • Star-delta overload relay sits in the phase windings and is set to about 0.58 × In. Changeover at about 90 % speed; the timer is usually 3–10 s.
  • VFD cabling: use a screened symmetrical motor cable with the screen terminated 360° in EMC glands at both ends. Above about 50–100 m of motor cable, add a dU/dt or sine filter as the maker requires.
  • Harmonics: many drives on one board raise THD. Consider drives with chokes, active front ends or filters, and size generators for them.
  • RCDs downstream of VFDs need the right type. See RCD types AC, A, F and B.
  • Fire pumps have their own controller rules, and the overload must not trip during a fire. See fire pump sizing.
  • On generators, the starter changes the set size. See the quick generator sizing method.

Typical values — verify with the edition adopted locally and with the motor and starter maker’s data.

Online course · certificate included

Electrical Power Systems Design for Buildings

35 modules from the MV connection to the socket: transformers, short circuit, protection and selectivity, cable sizing, boards, generators, earthing, surge and lightning protection. Includes 50 % off TEKHAT.

Modules 1–3 are free, no account needed · full course €15,00 one-time

Start freeView the course

FAQ

What is the maximum motor size for DOL starting?

There is no single limit. Many utilities allow about 5.5–7.5 kW DOL on public LV networks without permission. On a private transformer, much larger motors can start DOL if the voltage dip stays acceptable.

Is a soft starter better than star-delta?

A soft starter gives a smooth start without the changeover peak and allows a controlled stop, which helps against water hammer. Star-delta at 2–2.7 × In draws less current than a soft starter at 3–4 × In, so on a weak supply star-delta can be gentler.

When should I use a VFD instead of a soft starter?

Use a VFD when the speed should vary with demand, when the starting current must be as low as possible, or when a heavy load needs full torque from standstill. If the motor always runs at full speed, a soft starter is cheaper and simpler.

MEP Center software

TEKHAT – Single-Line Diagram & Load Schedule

Draw panel single-line diagrams and load schedules in minutes, with breaker, RCD and cable sizing. Buyers of the Electrical Power Systems Design course get 50 % off.

Free install from the Microsoft Store · 30-day trial · licence 20 € for all your devices or €15 per computer on our site

Get it from MicrosoftSee the program

Leave a Comment

Your email address will not be published. Required fields are marked *

Shopping Cart