Elevation of a building with the rolling sphere touching the roof edges and resting on two rods

Lightning Protection Basics: Rolling Sphere and Mesh Method

A lightning protection system is often drawn as “a rod on the roof and a cable to the ground”. Then the design review asks which parts of the roof are protected, and nobody can answer. The rolling sphere and the mesh method give a clear yes or no for every edge, parapet and rooftop unit.

Quick answer: Pick the protection class (LPL I–IV) from the risk assessment. That fixes the rolling sphere radius (20, 30, 45 or 60 m) and the mesh size (5, 10, 15 or 20 m). Roll the sphere over the building on every elevation: every point it touches needs an air termination, and everything it cannot touch is protected. On flat roofs, lay a mesh no larger than the class allows, with conductors on all edges. Use rods to protect rooftop equipment, then add down conductors and an earth ring.
Class (LPL / LPS)IIIIIIIV
Rolling sphere radius20 m30 m45 m60 m
Maximum mesh size5 × 5 m10 × 10 m15 × 15 m20 × 20 m
Typical down-conductor spacing10 m10 m15 m20 m
Design peak current200 kA150 kA100 kA100 kA

Step by step

  1. Set the class. Run the IEC 62305-2 risk assessment, or follow the national rule for the building type. Why: the class drives every other number, and “class I everywhere” wastes money.
  2. Draw the sphere on sections and elevations. In CAD, draw a circle of radius r and roll it over the building outline, touching the ground and the structure. Why: it shows exactly which edges, corners and tall parts can be struck.
  3. Put air terminations wherever the sphere touches. On a flat roof, that means conductors on all edges, parapets and ridges, plus a mesh no larger than the class allows. Why: most strikes hit corners and edges, not the middle of the roof.
  4. Protect rooftop equipment with rods. Between two rods or conductors the sphere sags by p = r − √(r² − (d/2)²), where d is the spacing. The equipment must stay below the rod tips minus p. Why: a unit that sticks out of the protected zone becomes the air terminal.
  5. Keep the separation distance. Calculate s = ki × (kc / km) × l between the LPS and metal parts or cables that are not bonded to it. Why: otherwise the strike flashes over into the building’s services.
  6. Run the down conductors. Use at least two, spread evenly and preferably at the corners, at the class spacing. Fit a test joint 0.3–1 m above ground on each one. Why: several paths split the current and lower the voltages along each conductor.
  7. Earth and bond. A type B ring about 0.5 m deep and about 1 m from the walls, or a foundation electrode, bonded to the main earthing terminal. Add a Type 1 SPD at the origin of the installation. Why: part of the lightning current enters the building through the incoming services.
Rolling sphere: what it touches needs an air termination r sag p Sphere touches both roof edges → air termination needed rooftop unit below the sag: protected by the two rods not to scale Down conductors on the walls, earth ring (type B) around the building r = 20 / 30 / 45 / 60 m for LPL I / II / III / IV
The sphere reaches both roof edges (red dots), so they need edge conductors. Between the two rods it sags by p but stays above the rooftop unit, so the unit is protected.

Worked example: rods over a rooftop unit

Data: class III (r = 45 m), two rods 2.5 m high and d = 10 m apart, rooftop unit 1.5 m high between them.
Sag: p = 45 − √(45² − 5²) = 45 − √2000 = 45 − 44.72 = 0.28 m.
Protected height at mid-span: 2.5 − 0.28 = 2.22 m > 1.5 m → protected.
Same layout in class I (r = 20 m): p = 20 − √(400 − 25) = 20 − 19.36 = 0.64 m → 1.86 m > 1.5 m → still protected.
Separation distance: class III, ki = 0.04, air km = 1, four or more down conductors with a ring kc ≈ 0.44, l = 20 m to the nearest bonding point → s ≈ 0.04 × 0.44 × 20 ≈ 0.35 m. Keep the unit’s metal casing and cables at least this far from the rods and conductors, or bond them.
Thatched roof with an air-termination wire on stand-off supports along the ridge lines and a down conductor at the eaves
Air-termination wire carried on stand-off supports along the edges of a thatched roof. On combustible roofs the conductors are held clear of the surface. Photo: HdeK, Public domain, via Wikimedia Commons

Common slips

  • Forgetting the walls of tall buildings. On a building taller than r, the sphere touches the facade above height r. Those upper edges and corners need air terminations too.
  • Using “special” air terminals to cover a large radius. Early streamer emission devices are not recognised by IEC 62305. Design with the sphere, mesh or angle method.
  • Undersized conductors. Copper 50 mm² (Ø 8 mm round) and hot-dip galvanised steel 50 mm² are the usual minimums for air terminations and down conductors.
  • No bonding of roof metalwork. Handrails, ducts and cable trays within the separation distance must be bonded or moved.
  • Earth ring not bonded to the main earth. The LPS earth and the electrical earth must be one system. See earthing systems explained and how to test the earth electrode.
  • No surge protection. An LPS without a Type 1 SPD at the origin lets part of the strike into the boards. See how to connect an SPD.

US projects follow NFPA 780, which also uses a rolling sphere, typically 46 m (150 ft) for ordinary structures, with air terminals at most about 6 m (20 ft) apart along roof edges.

Typical values — verify with the edition adopted locally.

Online course · certificate included

Electrical Power Systems Design for Buildings

35 modules from the MV connection to the socket: transformers, short circuit, protection and selectivity, cable sizing, boards, generators, earthing, surge and lightning protection. Includes 50 % off TEKHAT.

Modules 1–3 are free, no account needed · full course €15,00 one-time

Start freeView the course

FAQ

What rolling sphere radius should I use?

Under IEC 62305 the radius follows the protection class: 20 m for class I, 30 m for II, 45 m for III and 60 m for IV. The class comes from the risk assessment or the national rule for the building type. NFPA 780 uses 46 m (150 ft) for ordinary structures.

How do I calculate the sag of the sphere between two rods?

Use p = r − √(r² − (d/2)²), where d is the distance between the rods. For r = 45 m and d = 10 m, p is about 0.28 m, so equipment between the rods must stay at least 0.28 m below the rod tips.

When should I use the mesh method instead of the rolling sphere?

Use a mesh on flat or gently sloping roofs, with conductors on all edges and a cell size no larger than the class allows (5 to 20 m). Use the rolling sphere for complex shapes, tall parts and rooftop equipment. Most designs use both.

MEP Center software

TEKHAT – Single-Line Diagram & Load Schedule

Draw panel single-line diagrams and load schedules in minutes, with breaker, RCD and cable sizing. Buyers of the Electrical Power Systems Design course get 50 % off.

Free install from the Microsoft Store · 30-day trial · licence 20 € for all your devices or €15 per computer on our site

Get it from MicrosoftSee the program

Leave a Comment

Your email address will not be published. Required fields are marked *

Shopping Cart