Plan and section of a pipe run showing 42 m measured on plan versus 61.6 m installed with riser and drops

MEP Quantity Take-off: Practical Tips for BOQs

Most MEP bills of quantities go wrong in the same places: risers measured as dots on a plan, fittings forgotten, cable lengths taken “as the crow flies” and a waste factor hidden inside the numbers. A few habits make a take-off faster to produce and much easier for someone else to check.

Quick answer: Agree the measurement rules first (units, what is included in each item, net or gross). Then measure system by system and zone by zone from the latest drawing revision: pipes and cables by length per size including risers and drops, ducts by surface area per size range, and equipment, valves and fittings by count. Keep quantities net, show any waste allowance as a separate visible factor, and keep a trace from every BOQ line back to the sheets it came from.

Step by step

  1. Read the measurement rules before you measure. The contract or the client usually names a method of measurement or gives preambles: units, which fittings are included in the pipe rate, how supports and insulation are measured. Why: the same pipe run can be one line or six lines depending on the rules.
  2. Freeze the drawing set. Record the sheet numbers and revisions you are measuring from in the take-off header. Why: when a revision arrives, you can see at once which BOQ lines are affected.
  3. Split by system, then by zone or level. For example “Domestic cold water — Level 2” rather than one long list per discipline. Why: the client can compare zones, the site team can order per floor and errors stand out (a typical floor that is 40 % bigger than the others).
  4. Measure pipes and cables along the route, per size. Use the centreline on the plan, then add what the plan does not show: riser lengths from the riser diagram or sections, drops to equipment, and vertical rises at wall-mounted items. Why: a riser is only a circle on a plan, but it can be a quarter of the run.
  5. Count fittings and valves separately unless the rules include them. Bends, tees, reducers, isolating valves, strainers and flexible connections each get their own count per size. Why: on small-bore pipework the fittings can cost as much as the pipe.
  6. Measure ductwork by surface area. Rectangular duct area = 2 × (width + height) × length; group by size or gauge range as the rules require. Count dampers, grilles and diffusers, and measure insulation separately in m². Why: sheet metal is priced by area and thickness, not by running metre.
  7. Measure cables from board to load along the real route. Follow the tray or conduit route on the plan, add the riser height and a termination allowance at each end (into the board and up to the equipment). Why: straight-line cable lengths are always short.
  8. Keep quantities net; show waste separately. If your estimate needs an allowance, put it in its own column (for example 3–5 % on pipe) so a checker can see it. Why: waste hidden in quantities gets added twice — once by you and once in the rate.
  9. Mark what you have measured. Highlight each run on a copy of the drawing, or put measured objects on a “measured” layer, and tick off each schedule. Why: it is the only reliable way to prove nothing was missed or counted twice.
  10. Check against a rule of thumb. Compare totals per m² of floor area or per fixture with a similar past project. Why: a sanity check catches a dropped zero or a missing floor.
What the plan shows vs what gets installed Plan view Plant R-01 42 m measured riser = only a circle on plan Section L0L1L2L3L4L5 to plant: 42 m riser 16 m 0.6 m drop Plan 42.0 m + riser 16.0 m + drops 6 × 0.6 m = 3.6 m → 61.6 m installed Plan-only take-off: 42.0 m — about 32 % short
Risers and drops are invisible on a plan. Take them from the riser diagram and sections, not from the plan.

Worked example

Pipe run. Horizontal main measured on plan: 42.0 m. Riser over five storeys of 3.2 m: 5 × 3.2 = 16.0 m. Six branch drops of 0.6 m: 3.6 m. Net length = 42.0 + 16.0 + 3.6 = 61.6 m. If the estimate carries 3 % pipe waste, show it separately: 61.6 × 1.03 = 63.4 m to order — the BOQ line still reads 61.6 m.

Duct. A 600 × 400 mm duct, 25 m long: perimeter = 2 × (0.6 + 0.4) = 2.0 m, area = 2.0 × 25 = 50 m² of sheet metal; with 25 mm insulation, measure insulation as a separate 50 m² line (or as the rules define it).

Units at a glance

ItemUsual unitWatch out for
Pipes, conduits, cable traysm per size and materialRisers, drops, offsets around beams
Fittings, valves, supportsnr per sizeWhether the rules include them in the pipe item
Rectangular and round ductm² per size or gauge rangeFittings measured as extra area or counted
Insulation and claddingm² or m per sizeValves and flanges often get separate boxes
Cablesm per type and sizeRiser height, termination allowance, route not straight line
Equipment, fixtures, devicesnrCount from schedules, then cross-check on plans

Taking quantities from a model

A BIM model schedule is a fast start, not a finished BOQ. Check that every element is modelled at a level of development that supports measurement (see BIM LOD for MEP models explained), that hidden or duplicated elements are excluded, and that supports, sleeves and small fittings — often not modelled — are added by rule. Clean layer names and system names make filtering much easier, so follow your MEP drawing layer and sheet standards. For vertical lengths, a clear riser diagram is the best source, and after MEP coordination the offsets around beams can add several per cent to pipe and duct lengths.

Free tool: MEP unit converter — switch between metric and imperial lengths, flows and pressures when a BOQ mixes units.

Typical values — verify with the edition adopted locally and with the method of measurement named in the contract.

MEP Center

Ready-made drawings and tools for your next project

CAD block libraries, detail drawings and AutoCAD tools made by practising MEP engineers.

Browse the storeFree calculators

FAQ

How is ductwork measured in an MEP BOQ?

Usually by surface area in square metres, grouped by size or sheet thickness range: perimeter times length for each duct size. Dampers, grilles and diffusers are counted, and insulation is measured as a separate item.

Should waste be included in BOQ quantities?

Normally no. BOQ quantities are measured net, and the contractor allows for waste in the rate. If your own estimate needs a waste factor, keep it in a separate, visible column.

Why are my pipe quantities always short?

Most often because risers, drops to equipment and offsets around beams are not visible on the plan. Take vertical lengths from the riser diagram and sections and add them per size.

MEP Center software

PAFTA – Sheet Splitter & Merger for AutoCAD

See a whole tender set as one drawing: merge a folder of DWG, DXF and vector PDF files, convert vector PDF to DWG and split any drawing back into sheets.

Free install from the Microsoft Store · 30-day trial · licence 20 € for all your devices or €15 per computer on our site

Get it from MicrosoftSee the program

Leave a Comment

Your email address will not be published. Required fields are marked *

Shopping Cart